As spring approaches, we’ve received even more requests that usual for an update on construction of the new Ravenswood Metra Station. We reached out to 47th Ward Alderman Matt Martin’s office for the latest and are excited to shed some light on next steps and a projected timeline for the end of work. Read more “Ravenswood Metra Station Construction Update – February 2022”
Tag: Ravenswood Metra Station
Ravenswood Metra Construction Update August 2021
As of August 23rd, Leland Ave will be closed to traffic under the Metra tracks so that crews can install the new station’s platform. This closure is expected to last two weeks. Workers will maintain pedestrian access under the bridge and reopen one lane to traffic during the weekends. Read more “Ravenswood Metra Construction Update August 2021”
Ravenswood Metra Construction Update – May 2021
As crews continue construction of the new Metra Station at Ravenswood and Lawrence, the 4700 block of Ravenswood Avenue will experience a partial closure. We’ve got the details! Read more “Ravenswood Metra Construction Update – May 2021”
Ravenswood Metra Construction Update – Oct. 2020
The Beginning of the End Metra construction in Ravenswood feels like it’s been going on forever but the end is finally in sight! The final phase of Metra’s bridge renovation project is starting with the demolition of the old bridges from Grace to Balmoral. Crews will tear down two bridges per week, with a full […] … Read more “Ravenswood Metra Construction Update – Oct. 2020”
Ravenswood Metra Construction Update – Sept. 2020
We’ve got updates on the ongoing Metra bridge renovation project, which is about to enter its final stage. Concurrently, work on the new Ravenswood Metra Station is starting up again. Read more “Ravenswood Metra Construction Update – Sept. 2020”